Dubai Metro's Route 2020 project on track for completion

Supplied

Dubai Metro's Route 2020 project is on track for completion, with the Roads and Transport Authority (RTA) revealing that 70 per cent of the construction has finished.

The details were revealed by Mattar Al Tayer, Director-General and Chairman of the Board of Executive Directors of RTA, during an inspection tour of several stations including Expo, Al Furjan and Nakheel Harbour & Tower Stations. 

The completion rate had hit 80 per cent on the rail track work and 50-60 per cent for the station works of Route 2020 Project.

All rail works of Route 2020 are scheduled for completion by May 2019, with the RTA starting the test-run of the metro in February 2020.

 

 

More from Local

Coming Up on Dubai Eye

  • The Business Breakfast

    6:00am - 10:00am

    The Business Breakfast is the day’s must listen for the UAE’s business leaders, and those who aspire to be.

  • The Agenda

    10:00am - 1:00pm

    Broadcasting every weekday, Georgia Tolley goes beyond the headlines to speak to government ministers, decision makers, analysts and local experts to find out how the news will impact those of us living in the UAE.

BUSINESS BREAKFAST LATEST

On Dubai Eye

  • Is There Sufficient House Supply In UAE

    Dubai’s current population is more than double compared to almost twenty years ago, which now stands at 3.7 million. Lots of families are also moving to the UAE now. So what does it mean for the property market?

  • Noon's First Female Delivery Driver

    Glory Ehirim Nkiruka is Noon’s first ever female delivery driver. In her first ever interview, she explained why she loves her job, despite the heat!