DXB's northern runway renovation crosses half-way mark

File Picture

Dubai Airports (DXB) said the northern runway will reopen as per schedule on June 22, as renovation work crosses the half-way mark.

In a statement, Dubai Airports said the renovation project will see "the resurfacing of the 4.5 km-long runway, strengthening of the wider runway strip, as well as reinforcing the paving on key taxiway entries and exits, and repairing of the drainage infrastructure".

Aeronautical ground lighting, navigational aids and meteorological equipment are also being replaced, and a navigation aids substation is being relocated.

More than 1,000 vehicles and 3,000 people have been working on-site at DXB since work began on May 9.

The primary objective of the project is to "enhance the safety, operational efficiency, and capacity at DXB". 

During the 45-day closure, more than 1,000 flights from several international carriers, including flydubai, SpiceJet, Indigo, Gulf Air, Air India Express and Qatar Airways were shifted to the Dubai World Central (DWC).

More from Local

Coming Up on Dubai Eye

  • The Reboot

    10:00am - Noon

  • The Best of Dubai Eye 103.8

    Noon - 7:00pm

    Hear the highlights from the week gone by on Dubai Eye 103.8. Listen again to the best interviews, advice and the top stories that has gripped our conversation this week.

BUSINESS BREAKFAST LATEST

On Dubai Eye

  • Is There Sufficient House Supply In UAE

    Dubai’s current population is more than double compared to almost twenty years ago, which now stands at 3.7 million. Lots of families are also moving to the UAE now. So what does it mean for the property market?

  • Noon's First Female Delivery Driver

    Glory Ehirim Nkiruka is Noon’s first ever female delivery driver. In her first ever interview, she explained why she loves her job, despite the heat!